Construction Estimate Dashboard

Construction Estimate

11 Patriots Rd, Templeton, MA

Loan #

DR-2023-001

Budget Total

$320,000.00

Initial construction budget

Budget Estimated

$219,675.69

Current estimated costs

Budget Spent

$76,819.22

Amount already paid

Budget Remaining

$243,180.78

Available for remaining work

Budget Utilization

24.01%
$0 $320,000

About 24% of the total budget has been utilized so far, with significant funds remaining for ongoing and future construction phases.

Construction Line Items

Detailed breakdown of budget allocation and spending

Line Item Description Prev. Est. Actual Est. Paid Budget Remaining
Plans / Permits $6,000.00 $0.00 $0.00 $6,000.00
Demolition $15,000.00 $0.00 $0.00 $0.00
Foundation New Footings $15,000.00 $0.00 $0.00 $0.00
Roof / Gutters $28,000.00 $0.00 $0.00 $0.00
Exterior / Siding $30,000.00 $30,000.00 $0.00 $30,000.00
Windows All Windows Including Bay Window $15,600.00 $15,000.00 $0.00 $15,600.00
Framing Labor $75,000.00 $55,000.00 $25,000.00 $55,000.00
Framing Material $0.00 $18,675.69 $22,411.51 $35,000.00
Total Construction Cost $391,600.00 $219,675.69 $76,819.22 $329,600.00

Key Observations

Significant Budget Remaining

About 76% of the budget ($243,180.78) remains unspent, indicating most major construction work is still ahead.

Cost Savings in Framing

Framing labor was estimated at $75,000 but actual estimate is $55,000, representing potential savings of $20,000.

Materials Overpayment

Framing materials show $22,411.51 paid against $18,675.69 estimated - this overpayment should be investigated.

Exterior Work On Track

Exterior/Siding is fully estimated at $30,000 with no payments made yet - budget appears properly allocated.

Construction Estimate Report generated on June 15, 2023

For questions, contact the project manager at pm@constructionco.com